5 Commissioning
Before powering up the PV system it is important to check the installation for
any hazards that may be present. For convenience, a commissioning checklist
is included in this manual and can be found in the Appendix.
5.1 Mechanical Installation check
Make sure that the mounting bracket is secure, and all screws have
been tightened to the specified torque values. (Refer to 3.2
Mechanical
Installation)
Confirm all knockouts are sealed and conduit is securely attached to
the inverter, creating a water-tight seal.
5.2 Conductor Connections check
Make sure all conductors are connected to the right terminals and
properly labeled.
The appropriate cable management is important to avoid physical
damage. No sharp edges from cable ties exist.
Check polarity of DC input conductors. The DC Switch should be in the
“OFF” position. (Refer to 3.3 Electrical Installation
)
5.3 Electrical Check
Make sure that the AC circuit breaker is appropriately sized.
Test whether the AC voltage is within the normal operating range.
Confirm the DC open circuit voltage of input strings is less than 1000V.
Note: If either Tigo, APsmart, or NEP MLPE RSD products are installed
and in the OFF position, each module will measure 0.6Vdc. Ensure the
DC open circuit voltage of input strings will be less than 1000V when
power is supplied to the Rapid Shutdown transmitter, if applicable.