While harbour operation is activated, either by a digital input or a signal from CustomLogic, the operation overrides the EDG max.
parallel time. During harbour operation the emergency genset is treated as an ordinary genset with the first priority and all normal
GENSET controller protections.
During harbour operation, the EMERGENCY genset controller can be forced under switchboard control by alarms that force the
other controllers under switchboard control, or by the Power management > Force all controllers in section to SWBD control input. In
this case, the EMERGENCY genset controller stays under switchboard control, and does not automatically start the emergency
genset during a blackout.
Inputs and outputs
Assign the Harbour operation digital input under Configure > Input/output. Select the hardware module, then select the digital input
to configure.
Table 9.7
Additional wiring required to the minimum standard controller wiring
Function I/O Type Details
Power management >
Harbour operation
Digital input Continuous
The controller can run the emergency genset in long time parallel with the
main busbar when this input is activated. The emergency genset will have
the same protections as a standard genset when activated.
Optional: Assign the Harbour operation active digital output under Configure > Input/output. Select the hardware module, then
select the digital output to configure.
Table 9.8
Optional wiring
Function I/O Type Details
Power management
> Harbour operation
active
Digital
output
Continuous Activated when the Harbour operation digital input is activated.
Power management
> Allow harbour
operation
Digital
input
Pulse
This digital input only has an effect if the Operator confirms harbour operation
parameter is Enabled.
After the Harbour operation digital input is activated, activate this digital input to
confirm that harbour operation is allowed. This has the same effect as pressing
the Allow soft key then OK on the display unit.
Power management
> Reject harbour
operation
Digital
input
Pulse
If the emergency genset controller is in harbour operation and this input is
activated, then harbour operation is cancelled and the genset returns to normal
operation.
If the Operator confirms harbour operation parameter is Enabled, then after the
Harbour operation digital input is activated, this digital input has the same effect
as pressing the Reject soft key then OK on the display unit.
Note: This is a pulse function. If this digital input is continuously activated, it will
NOT prevent or stop harbour operation.
Parameter
Configure this parameter in Parameters > Local power management > Emergency generator.
Parameter name
Range Default Comment
Operator confirms
harbour operation
Not enabled,
Enabled
Enabled
Not enabled: No confirmation is required for harbour operation.
Enabled: The operator must use the display unit or Allow harbour
operation digital input to confirm harbour operation.