7 System Testing
It is recommended that at a minimum, the panel should be completely tested after it is
installed and placed into service. This test should include:
Confirming the display and leds are all functioning.
All of the display switches are functioning.
Confirming all wire connections are proper and tight.
The panel will recognize an AC Failure by removing the AC voltage with the
Standby battery is connected.
The panel will report a low/missing Standby battery by removing the battery while
the panel is AC powered.
Test each of the input circuits and confirming the proper box number is programmed
for each input. Also confirm that the panel was decoded properly at the dispatching
center.
Test the ability of the Det-16 to transmit in Ground Mode. Confirm that the Det-16
was decoded properly at the dispatch center.
Any other testing as required by the local jurisdiction having authority.