JT40/JT40 All Terrain Operator’s Manual Systems and Equipment - 183
Pipeloader
.
11. Remove pipe from auxiliary pipe loaders and store properly.
12. Repeat steps 8-10 to unload remaining added drill pipe.
13. After all added drill pipe is unloaded with auxiliary pipe loaders:
• Close both auxiliary pipe loaders.
• Remove pipe stop and store it on shuttle guard.
14. Press left side of auxiliary pipe load restricted operating mode switch to enable drill operator control of
shuttles and lifter.
15. Finish loading remaining drill pipe into last row using standard procedure. See “Remove Pipe” on
page 143.
Crushing weight could cause death or serious injury. Use
proper procedures and equipment or stay away.
To help avoid injury:
• Drill pipe is heavy. Have enough people on hand to manually add or remove single pipe to pipe box.
• Do not attempt to move shuttles until everyone is at least 10 ft (3 m) away from machine.
• Ensure switch operator is standing clear of all moving parts while removing pipe.