2. Main Connections and Temporary Operations
According to the ”Temporary Operations” page of the electrical wiring diagrams schematic page:
1) Connect the main power supply
2) Connect the traction motor and Brake Resistor
3) Connect the brake
4) Connect the Motor temperature sensor
5) Connect the inspection box for temporary operations (Using the Temporary Cable) connecting
them to the Screw terminals
6) Switch on main power
7) Carry out the Motor Tuning procedure (traction only) (Annex IV)
8) Install the Electrical System (Quick Installation Guide)