9. Slowly roll the cabinet toward
the ramp edge. Do not to push
the cabinet too much or too fast
because the cabinet can tip
over.
Note that the cabinet is heavy.
Make sure that you have
enough manpower to handle
and support the unit while rolling
it off the pallet.
10. Roll the cabinet to its final
installation location.
11. To secure the UPS cabinet in
position, lower the leveling feet
until the cabinet is not resting on
the casters and the cabinet is
level.
Note: If you remove the cabinet from its original installation location and
transfer it to a new location on a pallet, lower the leveling feet until the cabinet
is not resting on the casters. In addition, attach the shipping brackets to the
cabinet and the pallet.
Eaton 93PM UPS 30–200 kVA User's and installation guide
©
Eaton Corporation plc 2017. All rights reserved. Revision: 005 Document ID: P-164000249 49 (126)

Table of Contents

Other manuals for Eaton 93PM

Related product manuals