UPS System Installation
Eaton 93PM UPS (20–100 kW, 480V – 100 kW Frame) Installation and Operation Manual P-164000227—Rev 6 www.eaton.com/powerquality 4-33
Installation Checklist
o All packing materials and restraints have been removed from each cabinet.
o The UPS cabinet is placed in its installed location.
o All conduits and cables are properly routed to the UPS and any ancillary cabinets.
o All power cables are properly sized and terminated.
o Battery cables are terminated on E4 (+) and E5 (–).
o Battery shunt trip signal wiring is connected from the UPS to the battery disconnect.
o Battery detect signal wiring is connected from the UPS to the battery disconnect.
o A ground conductor is properly installed.
o Building alarms and alarm relays are wired appropriately. (Optional)
o LAN drops are installed. (Optional)
o LAN connections have been completed. (Optional)
o The REPO device is mounted in its installed location and its wiring is terminated inside the
UPS cabinet. (Optional)
o A jumper wire is connected between pins 3 and 4 on the REPO terminal block if using a normally-closed
REPO switch. (Optional)
o All internal safety shields are installed.
o Accessories are mounted in installed locations and wiring is terminated inside the UPS cabinet. (Optional)
o Air conditioning equipment is installed and operating correctly.
o The area around the installed UPS system is clean and dust-free. (Eaton recommends that the UPS be
installed on a level floor suitable for computer or electronic equipment.)
o Adequate workspace exists around the UPS and other cabinets.
o Adequate lighting is provided around all UPS equipment.
o A 120 Vac service outlet is located within 7.5m (25 ft) of the UPS equipment.
o Startup and operational checks are performed by an authorized Eaton Customer Service Engineer for parallel
systems or installations with accessory cabinets.