Commissioning via operating menu Levelflex FMP51, FMP52, FMP54 FOUNDATION Fieldbus
96 Endress+Hauser
11 Commissioning via operating menu
11.1 Installation and function check
Make sure that all final checks have been completed before you start up your measuring
point:
• Checklist "Post-installation check" → 55
• Checklist "Post-connection check" → 61
11.2 Setting the operating language
Factory setting: English or ordered local language
X X X X X X XX X
20.50
Operation
Setup
Main menu
0104-1
Language
English
Español
Français
Language
English
Deutsch
Ã
0104-1
Ã
Español
Français
Language
English
Deutsch
0104-1
Betrieb
Setup
Hauptmenü
Sprache
Deutsch
0104-1
XXXX
A0013996
21 Using the example of the local display
11.3 Checking the reference distance
This section is only valid for FMP54 with gas phase compensation (product structure:
feature 540 "Application Package", option EF or EG).
Coax probes with gas phase compensation are calibrated on delivery. Rod probes, on the
other hand, must be recalibrated after mounting:
After mounting the rod probe in the stilling well or bypass, check and - if necessary -
correct the setting of the reference distance in the unpressurized state. Whilst doing so the