4. 5 Post-connection check
Perform the following checks after completing electrical installation of the measuring device:
Device condition and specifications Notes
Are cables or the device damaged (visual inspection)?
Electrical connection Notes
Does the supply voltage match the specifications on the nameplate? 9 to 32 V DC
Do the cables used comply with the specifications? Fieldbus cablePage 20
Signal cablePage 23
Do the cables have adequate strain relief?
Are the power supply and fieldbus cables correctly connected? See the wiring diagram inside the cover
of the terminal compartment
Are all terminals firmly tightened?
Are all the cable entries installed, tightened and sealed?
Cable run with "water trap"?
Page 28
Are all the housing covers installed and tightened?
Electrical connection of FOUNDATION Fieldbus Notes
Are all the connecting components (T-boxes, junction boxes, connectors, etc.)
connected with each other correctly?
Has each fieldbus segment been terminated at both ends with a bus terminator?
Has the max. length of the fieldbus cable been observed in accordance with the
FOUNDATION Fieldbus specifications?
Page 21
Has the max. length of the spurs been observed in accordance with the
FOUNDATION Fieldbus specifications?
Page 21
Is the fieldbus cable fully shielded and correctly grounded? Page 21