Maintenance 8. Arm #4
154 G6 Rev.21
8.2 Replacing the Timing Belt
Name Quantity Note
Maintenance
parts
U1 belt (width 9 mm)
1
R13B030207
U2 belt (width 20 mm)
1
R13B030208
Tools
Hexagonal wrench (width across flats: 3 mm)
1
For M4 screw
Force gauge
1
Belt tension : 70N, 80N, 130N
(7.1 kgf, 8.2 kgf, 13.2 kgf)
Nippers
1
For cutting wire tie
Suitable cord (Length about 800 mm)
1
For belt tension
A brake is mounted on the motor of Joints #3 and #4 to prevent the shaft from moving
down due to the weight of the end effector while the power to the Controller is OFF or
while the motor is in OFF status (MOTOR OFF). (The brake for Joint #4 is only installed
to G6-**3**.)
Note that the brake will not work during the replacement procedure.
Move the shaft down to its lower limit before the replacement procedure following the
removal steps from (1) to (3).

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Epson SCARA ROBOT and is the answer not in the manual?

Epson SCARA ROBOT Specifications

General IconGeneral
BrandEpson
ModelSCARA ROBOT
CategoryRobotics
LanguageEnglish

Related product manuals