2.1 Preparing the CP system for operation
on the PROFIBUS-DP
2.1.1 Operating voltage
PLEASE NOTE
The CP fieldbus node must be supplied with opera-
ting voltage by a suitable power unit.
2.1.2 Saving the string assignment
PLEASE NOTE
Before commissioning the CP system, you must first
prepare the CP system for commissioning
(see "CP system" manual).
2. Commissioning
CP FB13-E 9904b 2-3