Operations 30
7.
Install the SPI board and tighten the thumbscrews.
8. Install the processor memory drawer ("Remove the processor memory drawer cover" on page 32, on
page 31).
9. Install the access panel (on page 26).
10. Install the server into the rack ("Installing the server into the rack" on page 38).
11. Connect each power cord to the server.
12. Connect each power cord to the power source.
13. Power up the server ("Powering up the server" on page 24).
Processor memory drawer shipping screw locations
Two orange shipping screws secure the processor memory drawer in place during shipping. You must
remove the screws to access the processor memory drawer. Retain the screws for future use.