Step 9 Connect the cable to the RAID controller card.
For details, see 7 Internal Cabling.
Step 10 Install the server node.
For details, see 8.3.4 Installing an XH321 V5.
Step 11 Power on the server node.
For details, see 8.3.1 Power-On Procedure.
Step 12 Congure the RAID controller card.
For details, see
Huawei V5 Server RAID Controller Card User Guide
.
----End
8.4.5 Removing the Supercapacitor (Server with a Screw-in
RAID Controller Card)
Procedure
Step 1 Power
o the server node.
For details, see 8.3.2 Power-O Procedure.
Step 2 Remove the server node.
For details, see 8.3.3 Removing an XH321 V5.
Step 3 Place the server node on the ESD workstation.
Step 4 Determine the position of the supercapacitor.
Step 5 Remove the air duct for the supercapacitor.
Step 6 Remove the supercapacitor holder.
1. Loosen the screws on the server node panel. See (1) in Figure 8-20.
2. Remove the panel. See (2) in Figure 8-20.
3. Loosen the screws that secure the supercapacitor holder and remove the
supercapacitor holder. See (3) in Figure 8-20.
FusionServer Pro XH321 V5 Server Node
Maintenance and Service Guide 8 Parts Replacement
Issue 17 (2021-03-09) Copyright © Huawei Technologies Co., Ltd. 58