1. Pre-install nuts according to the recommended torque of 27 N·m.
2. Verify that the torque of the installed bolts is 27 N·m using a torque wrench.
3. Mark the nuts whose torque has been veried using a marker.
Figure 5-11 Connecting the four-core AC input power cables (excluding the
ground cable and including the neutral wire)
(1) Screw assembly (2) Spring washer (3) Large washer (optional)
(4) Wiring terminals (5) Copper bar (6) Flat washer
LUNA2000-2.0MWH-1H0, 2H0 Smart String ESS
User Manual 5 Installing Cables
Issue 02 (2021-11-15) Copyright © Huawei Technologies Co., Ltd. 96