CA UTION
For non-emergency manual operations, do not remove the safety pull ring.
----End
4.3.5 Installing the Battery in the Fire Control Panel
Prerequisites
If a battery is damaged, contact your local oce.
In an outdoor scenario, you are advised to power on the re control panel
within 24 hours after unpacking. Otherwise, place it in a dry indoor
environment without corrosive gas.
Determine the position of the
re control panel.
Figure 4-16 Position of the re control panel
CA UTION
Do not damage components in the re control panel during the installation.
Procedure
Step 1 Open the re control panel and remove the cover.
Step 2 Install the battery and cover in the re control panel.
Step 3 Connect battery cables to the
re control panel.
NO TE
To verify that the battery connection of the re control panel works properly, perform the
following steps:
1. Turn on the battery switch of the
re control panel and keep it running using the
battery power supply.
2. Turn o the battery switch of the re control panel.
LUNA2000-2.0MWH-1H0, 2H0 Smart String ESS