5.3 Installing DC Power Cables
Prerequisites
The ESS is not powered on.
The DC power cables have been pre-buried.
The OT/DT terminals have been crimped. For details, see B Crimping an OT
or DT Terminal.
Procedure
Step 1 Remove the protective cover
Figure 5-1 Removing the protective cover
Step 2 Remove the bae plates for the DC power cables.
Figure 5-2 Removing the bae plates for the DC power cables
LUNA2000-2.0MWH-1H0, 2H0 Smart String ESS
User Manual 5 Installing Cables
Issue 02 (2021-11-15) Copyright © Huawei Technologies Co., Ltd. 90