7.7 Powering On the Smart PCS
Precautions
● Before turning on the AC switch between the Smart PCS and the power grid,
check whether the AC voltage is within the required range using a multimeter.
(See the local power grid standard.)
● If the Smart PCS has not been used for six months or longer after being
installed, it must be checked and tested by professionals before operation.
Procedure
Step 1 Turn on the AC switch between the Smart PCS and the power grid.
Step 2 Turn on the DC switches between the Smart PCS and the DC LV Panel busbar.
Step 3 Deliver a startup command on the SUN2000 app, SmartLogger, or the
management system, and wait for the system to soft start.
Step 4 Observe the LED indicators to check the running status of the Smart PCS.
----End
Indicator Description
You can view the running status of the Smart PCS by observing the LED indicators
on the panel.
Figure 7-7 LED indicators
LUNA2000-2.0MWH-1H0, 2H0 Smart String ESS
User Manual 7 Powering On the System
Issue 02 (2021-11-15) Copyright © Huawei Technologies Co., Ltd. 115