Procedure
Step 1 Determine the reference points for installing the ESS on the concrete platforms.
Mark the reference points using a marker.
Step 2 On the basis of the reference points, mark the mounting positions for the four
corner ttings of the ESS using an ink fountain and a long soft measure tape.
NO TICE
When marking the positions for corner ttings, ensure that the four lines form a
rectangle.
Figure 4-1 Concrete platform columns
LUNA2000-2.0MWH-1H0, 2H0 Smart String ESS
User Manual 4 Installation