Figure 4-12 Positions of the copper bars
(1) Desiccant (2) Copper bar
Step 2 Press and open the battery pack cover on the right side.
Figure 4-13 Opening the battery pack cover
Step 3 Wear insulation gloves and install copper bars between battery packs.
CA UTION
Pre-install nuts according to the recommended torque of 27 N·m.
Verify the torque of the installed nuts using a torque wrench set to 27 N·m.
Mark the nuts whose torque has been
veried using a marker.
Use an extension rod for the torque wrench.
LUNA2000-2.0MWH-1H0, 2H0 Smart String ESS
User Manual 4 Installation
Issue 02 (2021-11-15) Copyright © Huawei Technologies Co., Ltd. 82