Figure 4-5 Position of the ground cable hole and pagoda connector cutting
(1) Ground cable hole
NO TE
The position for cutting the pagoda connector is for reference only. The actual cable usage
may vary.
Step 2 (Optional) Connect ground cables/ground lugs to the ground points of the ESS
enclosure.
Connect ground cables to the ground points of the ESS using M12x30
stainless steel bolt assemblies. The ground cables can be routed through
plastic-coated metal hoses based on site requirements.
Figure 4-6 Installing ground cables
Connect ground lugs to the ESS ground points using M12x30 stainless steel
bolt assemblies.
LUNA2000-2.0MWH Series Smart String ESS
User Manual 4 Installation
Issue 08 (2022-11-15) Copyright © Huawei Technologies Co., Ltd. 101