EasyManua.ls Logo

Huawei LUNA2000-2.0MWH Series - Page 126

Huawei LUNA2000-2.0MWH Series
264 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Figure 5-4 Routing the ground cables in from the top
If cables are routed in from the bottom of the socket, connect one end of the
cables (1762) to the ground points of the socket and the other end to the
reserved ground points on the rear panel.
Figure 5-5 Routing the ground cables in from the bottom
----End
Scenario 2
This procedure applies only to the models listed in the table below.
Models
Air Conditioner Position in the
Battery Cabin
LUNA2000-2.0MWH-1HX 1/2/4/5/7/8/10/11
LUNA2000-2.0MWH-2HX 1/3/5/7/9/11
LUNA2000-2.0MWH-2HX 2/4/6/8/10/12
NO TE
Cables 1755, 1758, 2066, 2065, 1761, and 1766 are pre-installed. Cables 1756, 1751,
1759, 1752, 1757, 1763, 1760, 1765, 1762, and 1764 need to be installed.
The cables to be installed can be obtained from the cable binding position shown in the
gure before installing the socket.
LUNA2000-2.0MWH Series Smart String ESS
User Manual 5 Installing Cables
Issue 08 (2022-11-15) Copyright © Huawei Technologies Co., Ltd. 116

Table of Contents

Other manuals for Huawei LUNA2000-2.0MWH Series

Related product manuals