Figure 5-6 Before installing the socket
(1) Cable binding position
Step 1 Select a 110 V or 220 V socket as required.
Step 2 Connect the live wire and neutral wire.
● Installing a 110 V socket
a. Connect the live wire and neutral wire from the mains to positions 1 and
2 of the XT9 terminal block.
Figure 5-7 Connecting the live wire and neutral wire from the mains
b. Connect the live wire (corresponding to cable 1751) and neutral wire
(corresponding to cable 1752) from the lower end of the switch to
positions 1 and 3 of the XT1 terminal block.
LUNA2000-2.0MWH Series Smart String ESS
User Manual 5 Installing Cables
Issue 08 (2022-11-15) Copyright © Huawei Technologies Co., Ltd. 117