Set the automatic calibration functions.
Parameter Description
Automatic SOC calibration If this parameter is set to Enable,
automatic charge and discharge
calibration is allowed for battery
racks. During calibration, the cut-
o SOC settings will be
ineective and the response of
the charge and discharge power
may be impacted temporarily.
On-grid scenario: Automatic
charge calibration is allowed
for battery racks.
O-grid scenario: Automatic
discharge calibration is
allowed for battery racks.
If this parameter is set to
Disable, automatic charge and
discharge calibration is not
allowed for battery racks.
Automatic SOH calibration Set this parameter to Disable.
Set PCS insulation resistance detection.
Parameter
Description
Detection start time Set the start time of the PCS
insulation resistance detection. The
default value is 02:00.
If a dialog box You are advised to
change the insulation resistance
detection time to the optimal
time:
XX:XX
is displayed, you are
advised to click Conrm and set
Detection start time to the optimal
time.
Step 7 Connect to the Huawei NMS.
LUNA2000-(97KWH-1H1, 129KWH-2H1,
161KWH-2H1, 200KWH-2H1) Smart String ESS
User Manual 10 Commissioning the ESS (SmartLogger WebUI)
Issue 10 (2023-11-07) Copyright © Huawei Digital Power Technologies Co., Ltd. 152