9.3 Power-On Operations
D ANGER
Wear insulated gloves and use insulated tools to prevent electric shocks or short
circuits.
CA UTION
During the power-on procedure, power o the batteries immediately if any
fault is detected. Rectify the fault before proceeding with the procedure.
After batteries are used for system commissioning or batteries have discharged,
charge the batteries in time. Otherwise, batteries may be damaged due to
overdischarge.
Battery overdischarge and damage may occur if batteries with low SOC are
stored. Batteries shall be recharged in a timely manner.
NO TICE
If the ESS has not been used for six months or longer after being installed, it must
be checked and tested by professionals before operation.
LUNA2000-(97KWH-1H1, 129KWH-2H1,
161KWH-2H1, 200KWH-2H1) Smart String ESS
User Manual 9 Powering On the ESS
Issue 10 (2023-11-07) Copyright © Huawei Digital Power Technologies Co., Ltd. 130