7 Installation
● Ensure that the power circuit breaker is OFF before installing batteries.
● When installing batteries, do not place installation tools, metal parts, or
sundries on the batteries. After the installation is complete, clean up the objects
on the batteries and the surrounding area.
● When moving batteries, do not remove protective components such as
protective covers or waterproof caps from battery terminals.
● Do not move or operate under the forklift tynes.
● You can operate the battery pack installation kit only after the forklift stops
moving.
7.1 Installation Preparations
7.1.1 Preparing Tools
● The tool pictures are for reference only.
● The tool tables may not list out some tools required onsite. Onsite installation personnel
and the customer need to prepare the tools based on the site requirements.