10 Commissioning the ESS
(SmartLogger WebUI)
For details about deployment commissioning in microgrid scenarios, see the
Commercial and Industrial Microgrid Energy Storage Solution Quick Guide.
This section describes deployment commissioning in the on-grid scenario.
Prerequisites
1. All devices onsite have been commissioned.
2. The system is powered on and alarms are cleared.
3. The commissioning equipment is available onsite.
4. Before the deployment, wait until the air conditioners adjust the temperature
inside the cabinet and the temperatures of all batteries to the specied
temperature range (5°C to 45°C).
The screenshots in this section correspond to FusionSolar V800R021C10SPC010. The
screenshots are for reference only.
10.1 Preparations and WebUI Login
Prerequisites
● The operating system of Windows 7 or later is supported.
● Browser: Chrome 52, Firefox 58, or Internet Explorer 9, or a later version is
recommended.
● It is recommended that a maximum of two users log in to the WebUI at the
same time.
Procedure
Step 1 Connect the network cable between the network port of the PC and the WAN or
LAN port of the SmartLogger. It is recommended that the PC be connected to the
LAN port of the SmartLogger.
LUNA2000-(97KWH-1H1, 129KWH-2H1,
161KWH-2H1, 200KWH-2H1) Smart String ESS
User Manual 10 Commissioning the ESS (SmartLogger WebUI)
Issue 10 (2023-11-07) Copyright © Huawei Digital Power Technologies Co., Ltd. 133