Step 5 Take out the delivered documents, such as the packing list.
Figure 7-5 Document position
Step 6 Take out the mounting kits delivered with the product.
NO TE
After opening the door, check the number of deliverables based on the packing list. If any
deliverable is missing, contact your dealer immediately.
Table 7-1 List of mounting kits
Hoisting conversion
bracket and screw
Anchor bracket, anchor bracket
screw, and expansion bolt
Leveling
spacer
Step 7 After closing the cabinet doors, move the ESS to the specied position.
NO TE
If a forklift cannot be used on the transport route (for example, there is a slope), use a
crane to move the ESS.
LUNA2000-(97KWH-1H1, 129KWH-2H1,
161KWH-2H1, 200KWH-2H1) Smart String ESS
User Manual 7 Installation
Issue 10 (2023-11-07) Copyright © Huawei Digital Power Technologies Co., Ltd. 83