EasyManua.ls Logo

Huawei UPS2000-G Series - Status

Huawei UPS2000-G Series
175 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Table 3-4 Post-installation check items
No. Item Expected Result
1 Cable routing Cables are routed properly according
to engineering requirements.
2 Cable connections All cables are tightened to specied
torques using a torque wrench,
connected correctly, and free of
damage.
3 Cable connections for USB
ports and network ports
Cables to USB ports and network ports
are connected correctly and securely.
4 Labels Labels are neatly attached to both
ends of each cable, and the
information on the labels is concise
and understandable.
5 Ground cable connections The UPS ground cable is securely
connected to the ground bar in the
equipment room. Check that the
resistance between the UPS ground
cable and the equipment room ground
bar is less than 0.1 ohm using a
multimeter.
6 Distances between cable ties Distances between cable ties are the
same, and no burr exists.
7 Operating environment The inside and outside of the cabinet
are free from conductive dust or other
sundries.
8 Cables short circuit Check that cables are open-circuited
using a multimeter or an insulation
resistance tester.
9 Circuit breaker specications AC input circuit breaker specications
of the equipment room ≥ Circuit
breaker specications of the AC PDB ≥
AC input circuit breaker specications
of the UPS
UPS2000-G-(6 kVA-20 kVA)
User Manual 3 Installation
Issue 21 (2022-10-13) Copyright © Huawei Technologies Co., Ltd. 49

Table of Contents

Other manuals for Huawei UPS2000-G Series

Related product manuals