Figure 3-7 Removing packing materials
Step 5 Remove the foam and moisture-proof bag, and take out the UPS.
Step 6 Check that the UPS is intact.
1. Visually inspect the UPS appearance for shipping damage. If it is damaged, notify the
carrier immediately.
2. Check that the fittings comply with the packing list. If some fittings are missing or do
not comply with the packing list, record the information and contact your local Huawei
office immediately.
Step 7 Place the UPS in the installation position.
----End
3.1.4.2 80 kVA UPS
Procedure
Step 1 Visually inspect the UPS appearance for shipping damage. If any shipping damage is founded,
report it to the carrier immediately.
Step 2 Use a pallet truck to transport the UPS to the installation position.
Step 3 Hold the sliding plate steadily, cut and remove the binding tape, and put down the sliding
plate gently, as shown in Figure 3-8.