Chapter: Installation
32 M10-17313-EN
• Spirit level (not supplied)
• 19mm combination wrench (part no. P632-484)
• 16mm thin open-ended wrench (part no. P632-482)
Make sure that the full weight of the frame is bearing down on the feet. If it is not, you
will not be able to adjust the feet.
1. Place a spirit level on the center of the base beam.
2. Use the 19mm wrench to loosen the lock nut (1) on each leveling foot.
3. Use the 16mm thin open-ended wrench to turn the level adjuster nut (2) on each foot
while you monitor the spirit level reading.
As you make adjustments, make sure that no more than 12 mm (0.5 in) of thread is
exposed.
If you expose more than 12 mm (0.5 in) of thread, there is a risk that the threaded
adapter can separate from the foot.
4. Rotate the spirit level 90 degrees to verify that the load frame is level side to side and
front to back.
5. When the machine is level, use the 16mm thin open-ended wrench to hold the level
adjuster nut (2) while using the 19mm wrench to tighten the lock nut (1) on each foot.
Power supply compatibility
The first step in the installation is to verify that the voltage and electrical plug are
compatible with the location’s power supply.
The power cord set and plug is based on the country to which the frame was shipped
and is compatible with the electrical requirements for that country.
Frames may overheat or suffer damage if connected to a power supply greater than
15% above the configured voltage.