363-208-011, Appendix 3
Test Head Installation
Issue 1 November 1998 A3-9
Circuit Pack Verification
Step 1:
Verify that the SMU, LAN, and PDC are in the ARM shelf.
Step 2:
Verify that the MDC, T8U, and PTU are in the MDS shelf(ves) of the
subscriber circuits or drops to be tested.
NOTE:
The T8U is required for TR-08 operation only.
Step 3:
Verify that the DLC software is as follows:
COT: R 3.03.01 (or later)