Technical Notice V1.0 / 01.09 Page 31 / 100
Model CSW 100/150 4
4.4 Commissioning
The unit has been checked, tuned and tested in
our workshops.
A. Make the hydraulic and electrical connections.
B. Fill the reservoir with liquid.
C. Start up the machine (1).
D. Check the rotation direction of the pump and the
exhaust fan.
4.5 Specific tuning
4.5.1 Draining the reservoir
A. Disconnect the outlet pipe.
B. Put the output pipe into an empty container.
C. Press the push button (2) on the front of the unit.
D. Release the button when the pump emits air.