Page 74 / 100 Technical Notice V1.0 / 01.09
11 Model CSW 3000/3500/4700
11.4 Commissioning
The unit has been checked, tuned and tested in
our workshops.
A. Make the hydraulic and electrical connections.
B. Fill the reservoir with liquid.
C. Start up the machine (1).
D. Check the rotation direction of the pump and the
exhaust fan.
11.5 Specific tuning
11.5.1 Draining the reservoir
A. Put a container under the tap (2) or the drainage
plug located under the chiller.
B. Open the drainage tap.
11.6 Close the drainage tap once the reservoir is emp-
ty.