Installation guidelines
3-13
User Guide Rel 1.0 Standard May 1999
Procedure 3-4 (continued)
Preparing the cabinet for installation
Requirements
You need the following tools and materials:
• one derrick (crane) capable of lifting 4,000 lbs (1,809 kg)
• two, 8-ft long (minimum) wire rope slings (each with 4,000 lbs [1,809 kg]
capacity)
• four connecting links to attach wire rope slings to the cabinet lifting eye
bolts
• 5/8 in. diameter rope, approximately 75-ft long (used as a tag line)
• standard hex-type security tool or 216-type tool
Action
Step Action
1
Open the doors of the main and of the end compartments. To open the
latches on the cabinet main and end doors, insert the tamper-proof wrench
into the cup seams hex bolt (see Figure 3-6).
2
Turn the wrench a few degrees clockwise to release the latch (see
Figure 3-7).
Note:
Do not over-rotate.
3
Secure the wind latch (see Figure 3-8).
4
Inspect the inside of the cabinet to make sure there is no damage to
equipment.
5
Clean all debris from the concrete pad.
6
Remove the battery tray cover.
7
Remove the two rubber gasket sections from the supplied installation kit.
8
Place each section into position on the foundation pad. Make sure that the
gasket is under the bottom of the cabinet when it is in placed (see Figure 3-9).
9
Close and latch the main compartment doors in preparation for cabinet
placement.
10
Keep the SPC and termination compartment door open and secured with the
wind latch.
Note:
If outside plant (OSP) cables are already installed through the pad
surface (see Procedure 3-5, “Routing the cables to the mounting pad”).
—continued—