Instructions regarding the spreading operation
47
7
7 Instructions regarding the spreading operation
The intended use of the machine includes compliance with the operating, main-
tenance, and service conditions in accordance with the manufacturer specifica-
tions. Spreading therefore always includes preparation and
cleaning/maintenance.
Carry out spreading operations in accordance with the sequence described
below.
Preparation
Installing the spreader on the tractor Page 54
Close metering slide
Presetting the mounting height Page 58
Filling in the fertiliser Chapter A.2 or chapter A.3
1
1. See the register of your machine (AXIS 20.2, AXIS 30.2 or AXIS 50.2)
Adjusting the application rate Chapter B.2
1
Setting the working width
- Selection of the correct spreading disc
- Adjusting the drop point
Chapter B.5
1
Chapter B.5.3
1
Spreading
Travel to the spreading location
Check the mounting height
Engage the PTO shaft
Open the slider and start spreading
Finish spreading operations, and close the
slides
Disengage the PTO shaft
Discharge residual material Chapter B.10
1
Cleaning/maintenance
Open metering slide
Remove the spreader from the tractor
Cleaning and maintenance
Chapter C
1
and AXIS mainte-
nance