Fig. 51: Layout for one passage
Preparing for one pass
u
Select a similar fertilizer from the fertilizing charts and set the spreader accordingly.
u
Set the mounting height of the machine as specified in the fertilizer chart. Make sure that the
mounting height includes the top edge of the trays.
u
Check the spreading elements (spreading discs, spreading vanes, outlet) for correct functioning
and completeness.
u
Place two collecting vessels one in front of another at a distance of 1 m in the overlap zones
(between the tracks) and one collecting vessel in the track (according to Fig. 51)
n
Run the spreading test with the determined open position for operation:
ü
Perform the test at the desired working speed.
u
Open the metering slide 10 m before the collection trays.
u
Close the metering slides approx. 30 m behind the collection trays.
If the quantity collected in the collecting vessels is insufficient, repeat the passage.
Do not change the adjustment of the metering slides.