11 Material Calibration
Solid Material Calibration
13. Tap on the valve symbol and CONV tab to enter into solid calibration.
14. Place an adequate catch container under the spreader discharge chute.
15. Make sure that sufficient material in the hopper and the system is safe to run.
16. Set gate position:
Manual - Change CAL Gate to match actual gate position
Readback - Adjust actual gate position on the truck
Auto - Set to a desired gate position for calibration
17. Press “CALIBRATION” button to proceed.
18. Turn CONV Knob and/or SPN Knob to run.
19. Stop when desired amount is reached.
20. Weigh the material and enter the value.
21. Press “CALIBRATION” Button to complete.
Note: Press “STOP” button to stop the process anytime during calibration.

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the REXROTH CS 550i and is the answer not in the manual?

REXROTH CS 550i Specifications

General IconGeneral
BrandREXROTH
ModelCS 550i
CategoryController
LanguageEnglish

Related product manuals