EasyManuals Logo

SDMO R 340 U User Manual

SDMO R 340 U
287 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #112 background imageLoading...
Page #112 background image
Pressing
1 on the test keypad brings up the following window for selecting the test type.
15/07/09 19 : 10 :00 GS 1 Operation Manu Faults Alarms
I1(A) 2701 F.P 0,9 L
Q (kVAr)
Speed (rpm) 1505
765
Operating time: 10 :05
+ Speed - Speed + U -U
- 1 -
Function keys
- 2 -
Synchronisation column
- 3 -
Power plant
measurements summary
Using the KERYS Tactil Man-Machine Interface, the under
load test is started by pressing the corresponding key.
Using the KERYS Tactil Man-Machine Interface, the off load
test is started by pressing the corresponding key.
After validation of the test, the
orange LED on the test keypad lights up steady.
During the start-up phase, and until the alternator voltage and generating set speed
stabilise, the
green LED underneath the symbol for the generating set flashes and
becomes steady at the end of this phase.
The installation is then controlled via the programmable controller in accordance with the configuration of the application:
normal/emergency source switchover
grid coupling
etc.
The Normal/Emergency switchover with grid coupling is only possible by carrying out a load test.
The purpose of the off load test is to start a single GS or to couple a power plant (x generating sets) to the
emergency busbar.
Important
Test selected
Select the test to be carried out
Under load
test
Esc
No load
test
110/285

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SDMO R 340 U and is the answer not in the manual?

SDMO R 340 U Specifications

General IconGeneral
BrandSDMO
ModelR 340 U
CategoryPortable Generator
LanguageEnglish

Related product manuals