5.2.2 Insulation resistance
5.2.2.1 Insulation resistance and polarization index
Measuring the insulation resistance and polarization index (PI) provides information on the
condition of the machine. It is therefore important to check the insulation resistance and the
polarization index at the following times:
Before starting up a machine for the 󹪝rst time
After an extended period in storage or downtime
Within the scope of maintenance work
The following information is provided regarding the state of the winding insulation:
Is the winding head insulation conductively contaminated?
Has the winding insulation absorbed moisture?
From this, you can determine whether the machine needs commissioning or any necessary
measures such as cleaning and/or drying the winding:
Can the machine be put into operation?
Must the windings be cleaned or dried?
Detailed information on testing and the limit values can be found here:
"Testing the insulation resistance and polarization index" (Page50)
Assembly
5.2Preparing for installation
1LE1, 1FP1/3, 1PC1/3 shaft height 63 ... 315
Operating Instructions, 11/2023, A5E38483075A 49

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens 1FP1/3 and is the answer not in the manual?

Siemens 1FP1/3 Specifications

General IconGeneral
BrandSiemens
Model1FP1/3
CategoryEngine
LanguageEnglish

Related product manuals