EasyManuals Logo

Siemens 1FP1/3 User Manual

Siemens 1FP1/3
140 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #79 background imageLoading...
Page #79 background image
Commissioning
7
Comply with the following when carrying out any work on the machine:
Comply with the general safety instructions (Page15).
Comply with the applicable national and sector-speci󹪝c regulations.
When using the motor within the European Union, comply with the speci󹪝cations laid down
in EN50110‑1 regarding safe operation of electrical equipment.
Note
Service Center
Please contact the Service Center if you require commissioning support.
7.1 Measures before commissioning
The following list of checks to be performed prior to commissioning does not claim to be
complete. It may be necessary to perform additional checks and tests according to the speci󹪝c
plant or system.
Once the system has been correctly installed, check the following prior to commissioning:
The machine is undamaged.
The machine has been properly installed and aligned.
The output transmission elements are set correctly for their type,
e.g. alignment and balancing of couplings, belt forces in the case of a belt drive, tooth forces
and tooth-󹪞ank backlash in the case of geared output, radial and axial clearance in the case
of coupled shafts.
All 󹪝xing screws, connection elements, and electrical connections have been tightened to
the speci󹪝ed tightening torques.
The operating conditions match the data provided in accordance with the technical
documentation, such as degree of protection, ambient temperature, etc.
Moving parts, for example the coupling, move freely.
All touch protection measures for both moving and live parts have been implemented.
Screwed-in lifting eyes are removed after installation or secured to prevent them from
becoming loose.
Before commissioning, attach the covers to guarantee the correct air guidance.
Ensure that all condensation drain holes are always located at the lowest part of the machine.
1LE1, 1FP1/3, 1PC1/3 shaft height 63 ... 315
Operating Instructions, 11/2023, A5E38483075A 77

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens 1FP1/3 and is the answer not in the manual?

Siemens 1FP1/3 Specifications

General IconGeneral
BrandSiemens
Model1FP1/3
CategoryEngine
LanguageEnglish

Related product manuals