6.1 Overview
Prerequisites
The device has been installed.
The device has been connected in accordance with the possible connection methods.
Ethernet connection has been established.
Steps for starting up the device
1. Apply the supply voltage
2. Parameterize the device using the powerconfig software
3. Apply the measuring voltage
4. Apply the measuring current
5. Check the measured values using the powerconfig software
Note
Check the connections.
Incorrect connection can result in malfunctions and damage to the device.
Before starting up the PAC3200T, check that all connections are correct.
Note
When performing an insulation test of the entire installation with AC or DC, the device should
be disconnected before starting the test.