8.3 Pre-Commissioning Process
Perform the necessary steps to complete the pre-commissioning process:
1. The customer must review the LV-NKN-CS-0006 pre-Commissioning Checklist and prepare
the VFD for the commissioning procedure.
2. Ensure the Pre-Commissioning checklist procedure is complete prior to arrival of Quali󹪝ed
Siemens Personnel for commissioning of the VFD.
Note
The VFD must be commissioned by Quali󹪝ed Siemens Personnel only.