EasyManuals Logo

Siemens siprotec 7SA6 User Manual

Siemens siprotec 7SA6
876 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #229 background imageLoading...
Page #229 background image
Functions
6-397SA6 Manual
C53000-G1176-C156-2
(address 1611) is set to below the minimum short-circuit current (approx. 10 %). This
also applies to the phase currents during earth faults or double earth faults.
In address
1630 1ph FAULTS you can choose whether a phase–to–earth loop shall
be selected in an earthed network during single–phase pickup without earth current
(I
E
–release). The setting 1ph FAULTS = phase-earth is useful if no or only little
earth current can flow via the measuring point in the event of earth faults. With
1ph
FAULTS
= phase to phase only the leading phase–phase loop is measured in
the event of a single–phase pick-up in the earthed network.
Two further general settings refer to the final times, i.e. the tripping times in a worst
case scenario for faults outside all distance zones. They should be set above the delay
times for distance zones providing a final back-up option (also see “Independent
ZonesZ1uptoZ5”inSection6.2.4.2).
The directional final time
DELAY FORW. PU (address 1602) only works with short cir-
cuits in forward (line) direction if there is no impedance within a distance zone after
pick-up.
The non-directional final time
DELAY NON-DIR. (address 1603)worksforallshort-
circuits if there is no impedance within a distance zone after pick-up.
U/I(/ϕ)Pickup The meaning of the settings can be seen from Figure 6-21. Iph> (section a, address
1611) is the minimum current as described in the previous section, Iph>> (section c)
is the overcurrent pick-up.
Figure 6-21 Parameters of U/I/ϕ pick-up
In most cases the angular dependence is not required. Then the voltage-dependent
sectionbisvalidwhichresultsinthecharacteristica-b-c.Whencontrollingwith
Uphe
in the addresses 1612 Uph-e (I>>) and 1613 Uph-e (I>) the voltages for
phase–to–earth are inserted to determine the voltage-dependent branch b; corre-
spondingly when using
Uphph the voltages for phase–to–phase are set in the ad-
dresses
1614 Uph-ph (I>>) and 1615 Uph-ph (I>). The relevant settings are
determined according to the “Pickup Mode” (see above).
The characteristic has to be set such that it is just below the minimum expected volt-
age at the maximum expected load current. If in doubt, check the pick-up conditions
in accordance with the U/I characteristic.
123
10
20
30
40
50
60
U
V
I
I
N
U(Iϕ>)
U(I>>)
U(I>)
Iph> Iϕ> Iph>>
Pick-up only
at ϕ>
Load Range
Pick-up Independent
from Angle
a
b
c
d
e

Table of Contents

Other manuals for Siemens siprotec 7SA6

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens siprotec 7SA6 and is the answer not in the manual?

Siemens siprotec 7SA6 Specifications

General IconGeneral
BrandSiemens
Modelsiprotec 7SA6
CategoryRelays
LanguageEnglish

Related product manuals