Installation and Commissioning
8-597SA6 Manual
C53000-G1176-C156-2
8.3.7 Current, Voltage, and Phase Rotation Checks
Load Current
10 % I
N
The connections of the current and voltage transformers are tested using primary
quantities. Secondary load current of at least 10 % of the nominal current of the device
is necessary. The line must be energized and remains energized during this measure-
ment test.
With proper connections of the measuring circuits, none of the measured-values su-
pervision elements in the device should pick up. If an element detects a problem, the
relevant condition can be viewed in the operational annunciations (refer also to Sub-
section 7.1.1.2).
If current summation errors occur, then check the matching factors. See Sub-section
6.1.1.
Messages from the symmetry monitoring could occur because there actually are
asymmetrical conditions in the network. If these asymmetrical conditions are normal
service conditions, the corresponding monitoring functions should be made less sen-
sitive. See Section 6.21.2.
Quantities Currents and voltages can be viewed as primary or secondary quantities in the front
display or via the service interface with a personal computer, and compared with the
actual measured values (refer to section 7.1.3.1).
If the measured values are not plausible, the connection must be checked and correct-
ed after the line has been isolated and the current transformer circuits have been
short-circuited. The measurements must then be repeated.
Phase Rotation The phase rotation must correspond to the configured phase rotation, in general a
clockwise phase rotation. If the system has an anti-clockwise phase rotation, this must
have been considered when the power system data was set (address
0235 PHASE
SEQ.
, refer to Sub-section 6.1.1). If the phase rotation is incorrect, the alarm 171
Fail Ph. Seq.
”(FNo171) is generated. The measured value phase allocation
must be checked and corrected, if required, after the line has been isolated and cur-
rent transformers have been short-circuited. The phase rotation check must then be
repeated.
Voltage
Transformer
Miniature Circuit
Breaker (VT mcb)
The VT mcb of the feeder must be opened. The measured voltages in the operational
measured values (Sub-section 7.1.3.1) appear with a value close to zero (small meas-
ured voltages are of no consequence).
Check in the spontaneous messages (section 7.1.1.7) that the VT mcb trip was en-
tered (message
>FAIL:Feeder VT ON in the spontaneous messages). Before-
hand it has to be assured that the position of the VT mcb is connected to the device
via a binary input.
Close the VT mcb: The above messages appear under the spontaneous messages
as
OFF”, i.e. >FAIL:Feeder VT OFF”).
If one of the events does not appear, the connection and routing of these signals
(Sub-section 5.2.4) must be checked.
If the
ON“–state and OFF“–state are swapped, the contact type (H–active or L–
active) must be checked and remedied (Sub-section 5.2.4).
If a busbar voltage is used (for voltage protection and synchronism check) and the as-
signed VT mcb is connected to the device, the following function must also be
checked:

Table of Contents

Other manuals for Siemens siprotec 7SA6

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens siprotec 7SA6 and is the answer not in the manual?

Siemens siprotec 7SA6 Specifications

General IconGeneral
BrandSiemens
Modelsiprotec 7SA6
CategoryRelays
LanguageEnglish

Related product manuals