Section 5 – Procedures Lift Cylinder Installation
5. Connect the electrical connector to the holding
valve coil.
6. Use the bolts and washers removed earlier to
secure the lift cylinder to the mast.
7. Put the mast cover on top of the mast.
8. Fasten it in place with the wing screws removed
earlier.