7.2 Commissioning procedure
If all of the items mentioned above meet the requirements, proceed as follows
to start up the inverter for the first time.
1. Turn the DC switch of the inverter to “ON” position.
2. Set initial protection parameters via the Solplanet App. For details, please refer to “8.4
Create a plant”.
3. Switch on the AC circuit breaker. If the irradiation and grid conditions meet requirements,
the inverter will operate normally.
4. Observe the LED indicator to ensure that the inverter operates normally.