Installaon Procedure — Temperature Probe
1. Locate the thermowell in the metering system.
2. Slide the temperature probe jacket over the temperature probe wire unl it covers the enre wire.
3. Screw the cable gland into the thermowell and ghten. Squeeze the Copper An-Seize on the metal p of the
temperature probe.
4. Slide the temperature probe into the thermowell. Compress the cable gland down onto the temperature probe.
5. Screw the cable gland into the back of the TCS3000 register and ghten.
6. Insert the temperature probe wiring into the cable gland. Wire the Temp. Probe into the Temp Probe locaon on
the terminal board. Leave a small amount of slack on the wiring.
7. Compress the cable gland on the TCS3000 register unl it is snug on the temperature probe wire.
8. Run the temperature probe wiring to the back of the TCS 3000 register. Insert the wiring into the third cable gland
from the top of the register as in the illustraon above.
9. Leave slack in the temperature probe wiring and ghten the cable gland down on the temperature probe. If
needed the probe wire may be trimmed of excess wire before ghtening down the cable gland.
10. Wire the probe into the TCS 3000 register as pictured.
Installaon Procedure:
3/8” Reference Port
Thermowell
RED
WHITE
RED
WHITE
Seal Wire
Drilled Washer
Spacer Lock
Jacket
Cable Gland
Temperature Probe
An-Sieze

Other manuals for TCS 3000

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the TCS 3000 and is the answer not in the manual?

TCS 3000 Specifications

General IconGeneral
BrandTCS
Model3000
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals