Document Ref 941113-001 Rev 2 Page 4-29
Quantium 310 Maintenance Manual Maintenance Procedures - Hydraulic
13) Position the new meter onto the pump and tighten the two screws on the pump connection
to secure in position.
14) Re-fit the meter outlet pipe to the top of the meter using new o-rings and secure in position
by tightening the two screws
15) Fit the new pulser into the pulser casing.
16) Using a 3mm allen key, re-fit and tighten the four screws on the pulser casing.
17) Apply new W&M seals to the pulser and meter.
18) Ensure that all tools and unused materials are removed.
19) Re-fit the hydraulic doors to the dispenser and lock.
20) Re-instate power to the dispenser.
21) Test operation of the new meter.
22) Dispose of all waste accordingly.