Deck Belt Installation (continued)
4. Install the left and right deck belt guards.
5. Install the oor pan assembly to the machine.
6. Connect the battery by installing the positive cable rst, then the negative
cable to the battery .
Deck Replacement
Deck Removal
1. Park the machine on a level surface and disengage the PT O. Stop the
engine, wait for all moving parts to stop and remove the key . Engage the
parking brake.
2. Disconnect the battery by removing the negative cable rst, then the positive
cable from the battery .
3. Remove the deck belt. Refer to Deck Belt Removal ( page 5– 7 ) .
4. Set the height-of-cut of the deck to transport height.
5. Placing blocks under the deck for support, remove the height-of-cut pin to
allow the deck to rest on the blocks. Lower the deck onto the supporting
blocks.
6. Using a 9/16 inch wrench, slowly loosen and remove the (3/8 inch) lift assist
spring shoulder bolt.
g431 180
Figure 46
7. Using a 9/16 inch socket, remove the 2 (3/8 inch) nuts and carriage bolts
securing the deck strut to the frame.
Deck: Service and Repairs Page 5–10 2000 Series Z MASTER®Service Manual