CVHE-SVX005C-EN
101
Both jumpers “Disconnected” for Non
Solidly Grounded System (Any Delta, High
Impedance Ground, or Ungrounded Wye).
Note: Refer to AFD-SVG002*-EN for more
information.
Dry run starter (non-Adaptive Frequency™
Drive [AFD]).
Measure condenser pressures and flow.
Adjust condenser flow sensing device.
Measure evaporator pressures and flow.
Adjust evaporator flow sensing device.
Measure optional heat recovery pressures and flow.
Adjust optional heat recovery flow sensing device.
Inspect motor starter panel and perform starter
panel checkout procedures.
Confirm proper phase check incoming power.
Inspect control panel.
Apply separate source 120 Vac power to control to
perform control panel checkout procedure.
Review and record unit configuration parameters.
Confirm oil pump pressure—regulating valve
setting.
Verify vane operator is working properly and moves
without binding.
Dry run test starter (non-AFD).
Remove separate source power and reconnect
wiring.
Install optional Air-Fi and/or Wi-Fi modules.
3. Preparation for Start-up
Relieve nitrogen holding charge.
Evacuate and charge the system.
Apply power to the starter panel.
Verify current to the oil sump heater.
4. Chiller Start-up
Set Purge mode to “On.”
Bump-start the compressor and verify compressor
motor rotation.
Start chiller.
Verify no unusual noises or vibrations and observe
operating conditions.
If necessary, adjust oil pressure regulator between
18 to 22 psid (124.1 to 151.7 kPaD) net.
Measure and verify refrigerant pump pressure.
When chiller is stable, take system log three times
at 15-minute intervals.
Set Purge mode to “Adaptive.”
Reset the “Starter Energy Consumption” resettable.
Record a Chiller Service Report.
Review “AdaptiView Display Customer Training
Checklist.”
Equipment Description
Stopping/Starting Chiller Operation
Alarms
Reports
Data Graphs
Equipment Settings
Display Settings
Security Settings
Basic Troubleshooting
Appendix C: CenTraVac™ Chiller Start-Up Tasks to be Performed by Trane

Table of Contents

Related product manuals